Comments on: PCC officials move forward with Rock Creek development plans – OregonLive.com /news/2010/11/pcc-officials-move-forward-with-rock-creek-development-plans-oregonlive-com/ Thu, 23 Dec 2021 20:13:45 +0000 hourly 1 https://wordpress.org/?v=6.9.4 By: Barbara Linn /news/2010/11/pcc-officials-move-forward-with-rock-creek-development-plans-oregonlive-com/#comment-25888 Mon, 06 Jun 2011 18:23:02 +0000 http://bond.pcc.edu/?p=1803#comment-25888 PROJECT UPDATE June 20110
We are starting to proceed with the schematic design phase for the addition of building 7.

In October 2011, we will proceed with the programming of buildings 3, 5 and 9. This past spring Jason Miller and I met with the campus stakeholders in buildings 2 and 7 and the West zone team to work out the scope of work for the Bond work in those areas.

By December 2011 we should be able to finalize our budget and the scope of work for the Bond Projects.

Next summer 2012 anticipated projects include:
1) New exit road to 185th from campus;
2) Deconstruction and addition to the east side of building 7
3) Phase I of the Farm upgrades
4) Stormwater upgrades

Stay tuned for more information later this summer.

]]>